Key Points
- Tower Hamlets Council has issued a preliminary market-engagement notice for a main contractor for the Augusta Street housing scheme in Poplar.
- The estimated construction contract is worth £58 million excluding VAT, or £69.6 million including VAT.
- The scheme is to provide 100 social rented homes across two buildings: a 14-storey higher-risk building and a six-storey residential block.
- The works are also to include a community hub, residents’ room, landscaping, amenity space and public-realm improvements.
- Augusta Street is described in the procurement notice as one of the Mayor’s priority projects.
- The council intends to use a Competitive Flexible procedure under the Procurement Act 2023.
- A market-engagement session is scheduled for 17 December 2026, from 12:30 to 13:30, via Microsoft Teams.
- Suppliers must register and submit preliminary responses by 5pm on 14 December 2026.
- The formal tender notice is estimated to be published on 2 February 2027.
- The council estimates the main construction contract will run from 9 September 2027 to 8 March 2030, a period of two years and six months.
- The council’s Future Places investment prospectus says Augusta Street will include more than 50 extra-care units and new general-needs affordable housing.
- The development forms part of the council’s direct housebuilding programme, which aims to deliver 1,100 homes over six years.
- The procurement notice identifies the opportunity as suitable for small and medium-sized enterprises.
- AtkinsRéalis was appointed as cost consultant for Augusta Street in February 2026 under a contract valued at £270,525, according to Tower Hamlets’ contracts register.
- Pick Everard was appointed for structural and civil engineering services on the same date, under a contract valued at £199,261, according to the same register.
Tower Hamlets Council (East London Times) November 2026 — Tower Hamlets Council has begun seeking a main contractor for a £58 million housing development at Augusta Street, beside Bartlett Park in Poplar, east London.
- Key Points
- How many homes will the scheme provide?
- What else will be built?
- Why is the building classed as higher risk?
- When will contractors be appointed?
- What procurement route will be used?
- What is the council’s wider housing programme?
- Who has already been appointed?
- What has the council said about housing priorities?
- Background of the development
- Prediction: What could this mean for local residents and suppliers?
The council published a preliminary market-engagement notice on the Find a Tender service on 23 November 2026 at 4:22pm. The notice, reference HAR6220, invites potential suppliers to learn more about the forthcoming procurement before the formal tender process begins.
According to the notice, the London Borough of Tower Hamlets is seeking to procure a contractor to carry out the main construction works on the Augusta Street scheme. The authority states that the procurement will use a Competitive Flexible procedure under the Procurement Act 2023.
The estimated total value is £58,000,000 excluding VAT and £69,600,000 including VAT. The notice classifies the opportunity as a works contract, with the relevant construction-work classification code 45000000.
How many homes will the scheme provide?
The Augusta Street scheme is expected to deliver 100 high-quality social rented homes across two residential buildings.
As reported in the council’s procurement notice, the development will comprise a 14-storey higher-risk building and a six-storey residential block. The notice describes the homes as social rented accommodation, rather than homes for sale or market rent.
The council’s Future Places investment prospectus provides further detail on the intended mix. It states that the Augusta Street scheme will deliver more than 50 extra-care units and new general-needs affordable housing.
The prospectus identifies Augusta Street as one of the council’s direct housebuilding projects due to be tendered in 2026, alongside Albert Jacob House. It says the council will look for construction partners for these sites during the year and welcomes early engagement on later sites.
What else will be built?
The proposed development is not limited to residential accommodation.
The procurement notice says the scheme will include a community hub, a residents’ room, associated landscaping, amenity space and public-realm improvements.
The council’s Future Places document similarly describes Augusta Street as an extra-care and affordable-housing scheme. It does not provide a breakdown of the number of general-needs affordable homes beyond describing them as “new general needs affordable housing”.
The site is adjacent to Bartlett Park in Poplar. A separate procurement notice for architectural services, published in 2025, referred to the project as the “Augustus Street (Bartlett Park) Extra Care Scheme” and described the land as adjacent to Bartlett Park.
Why is the building classed as higher risk?
One of the two proposed buildings is described as a 14-storey Higher Risk Building, or HRB.
The term appears in the procurement notice without further explanation of the building’s design, fire-safety measures or regulatory approvals.
Under England’s building-safety regime, higher-risk buildings are generally residential buildings at least 18 metres in height, or with at least seven storeys, containing at least two residential units. The notice does not state whether the Augusta Street building will require Gateway 2 approval before construction, although it asks prospective suppliers for feedback on “gateway 2 submissions”.
The council has not published a construction start date in the market-engagement notice. It has, however, estimated that the main construction contract will run from 9 September 2027 to 8 March 2030.
When will contractors be appointed?
The council has set out an initial timetable for suppliers interested in the contract.
Potential bidders must register their interest through the Proactis Procurement Portal, using project reference DN836869. They must submit attendee contact details, including name, position and email address, through the portal’s messaging function by 5pm on 14 December 2026.
Suppliers are also asked to complete four preliminary questions through Microsoft Forms. The council says the questions will seek market feedback on suppliers’ experience, Gateway 2 submissions and the proposed procurement approach, while allowing initial questions. Responses are anonymous and must be submitted by the same 14 December deadline.
The market-engagement session will take place online on 17 December 2026, from 12:30 to 13:30, via Microsoft Teams. The council says the session is advertised openly through the notice and that invitations will be sent a day or two before the event.
The formal tender notice is estimated to be published on 2 February 2027.
What procurement route will be used?
Tower Hamlets Council says it will procure the main contractor through a Competitive Flexible procedure under the Procurement Act 2023.
The notice does not publish detailed award criteria, evaluation weightings, a bidder shortlist or a final contract-award date. It does, however, state that the opportunity is considered particularly suitable for small and medium-sized enterprises.
The procurement is above the relevant threshold. The estimated value of £58 million excluding VAT is stated in the notice, alongside the VAT-inclusive figure of £69.6 million.
The contracting authority is listed as Tower Hamlets, with its public procurement organisation number given as PQBL-2673-MVYG. The notice provides the council’s procurement email address and website for further information.
What is the council’s wider housing programme?
Augusta Street forms part of Tower Hamlets Council’s direct housebuilding programme.
In its Future Places investment prospectus, the council says the programme will deliver 1,100 homes over the next six years. It identifies Augusta Street and Albert Jacob House as projects to be tendered in 2026.
The prospectus also sets out the council’s wider Mayor’s Accelerated Housing Programme. It says this comprises up to 3,500 homes across 46 council-owned sites, with a stated commitment that 51% will be affordable.
The document says the council’s direct delivery programme will deliver 1,100 homes, while the Mayor’s Accelerated Housing Programme has the potential to deliver a further 3,000 or more homes. It also says the council is enabling the delivery of 6,000 social rented homes through partnerships.
Who has already been appointed?
Two professional appointments connected to Augusta Street appear in Tower Hamlets Council’s contracts register.
The register records an award for “HAR6139: Cost Consultant – Augusta Street” as a multiple award involving seven suppliers. It gives an award date of 26 February 2026, a contract start date of 24 March 2026 and an end date of 31 March 2031. The recorded contract value is £270,525.procontract.due-north+1
AtkinsRéalis was appointed as cost consultant for the scheme in February 2026 under that contract. The register does not identify which of the seven suppliers received which portion of the recorded value.procontract.
The same register records “HAR6140: Structural & Civil Engineering Services – Augusta Street” as awarded to Pick Everard. It gives an award date of 26 February 2026, a contract period from 15 July 2026 to 14 July 2031, and a value of £199,261.
What has the council said about housing priorities?
The Future Places prospectus, which includes a foreword from Mayor Lutfur Rahman, sets out the council’s development priorities.
It says the council’s priorities include affordable homes, more family-sized housing to tackle overcrowding, improvements to public realm and community spaces, affordable workspaces, good jobs for local people and retaining existing families and communities.
The prospectus states that Tower Hamlets has delivered more than 55,000 homes in the past 20 years and that its current direct delivery programme will deliver 1,100 homes.
It also says the council granted planning permission for more than 21,000 new homes since April 2022 and granted planning consent for more than 9,000 homes in 2025 alone.
Background of the development
Augusta Street is a council-led housing scheme in Poplar, adjacent to Bartlett Park. It has been identified by Tower Hamlets Council as one of the Mayor’s priority projects and as part of its direct housebuilding programme.find-tender.
The council’s Future Places prospectus, published as part of its investment and development strategy, describes the Augusta Street scheme as providing more than 50 extra-care units alongside new general-needs affordable housing. It also identifies the project as one of two direct-delivery schemes expected to be tendered during 2026.
The latest procurement notice confirms that the scheme is now being prepared for a main-contractor procurement, with an estimated construction value of £58 million excluding VAT. It confirms that the development will provide 100 social rented homes, a community hub, a residents’ room and associated external works.
The appointment of cost consultants and structural and civil engineering consultants in February 2026 indicates that the council had already begun assembling professional support for the project before issuing the market-engagement notice. The contracts register records both appointments on 26 February 2026.procontract.
Prediction: What could this mean for local residents and suppliers?
For local residents, the development could increase the supply of social rented and extra-care housing in Poplar. If delivered as described, it would add 100 social rented homes, including more than 50 extra-care units according to the council’s Future Places prospectus, alongside community and public-realm facilities.find-tender.
For older residents and people with care needs, the extra-care element could provide housing designed to support independent living with access to care and support services. The council has not published details in the procurement notice on eligibility, care provision, rent levels, allocation arrangements or the expected completion date for individual homes.find-tender.
For construction firms, particularly small and medium-sized enterprises, the market-engagement process provides an early opportunity to understand the council’s requirements before the formal tender is published. The notice specifically identifies the opportunity as particularly suitable for SMEs and invites feedback on experience, Gateway 2 submissions and the proposed procurement approach.
For prospective bidders, the £58 million estimated contract value and estimated two-and-a-half-year construction period could make Augusta Street a significant works opportunity in east London. However, the final contract value, procurement requirements and award timetable may change after the market-engagement exercise and before the tender notice is published on 2 February 2027.
For the wider Tower Hamlets housing programme, the scheme represents one part of the council’s stated aim to deliver 1,100 homes through direct housebuilding over six years. Its progress will depend on the procurement process, construction programme and delivery of the wider housing pipeline described in the council’s Future Places prospectus.