Key Points
- Construction of Havering’s 300-place Balgores Special Free School is progressing in Gidea Park.
- First-floor concrete frames are in place and excavation for the hydrotherapy pool is complete.
- Work has begun on the sports hall, while a sewer network is being constructed.
- The school will serve pupils aged four to 19 with special educational needs and disabilities.
- The project is funded by a £38 million Department for Education grant.
Gidea Park (East London Times) November 18, 2026 – Work is well underway on the new Balgores Special Free School in Gidea Park, with first-floor concrete frames installed and excavation for its hydrotherapy pool completed. Havering Council said developers Galliford Try had also started construction of the sports hall and were building a sewer network. The 300-place school will provide specialist education for children and young people aged four to 19 and is intended to expand local provision for pupils with special educational needs and disabilities.
What progress has been made at the new Gidea Park school?
Havering Council said the project had reached several key construction stages. First-floor concrete frames are now in place, excavation for the hydrotherapy pool has been completed and construction of the sports hall has begun. A sewer network is also being built, according to the council’s account of a site tour.
Councillor Kevin Gill, Havering Council’s Cabinet Member for Children and Young People, toured the site with Council Leader Councillor Keith Prince and local ward councillors. The council said Galliford Try provided the update during the visit.
What facilities will the Balgores Special Free School provide?
The planned school will accommodate 300 pupils aged four to 19. Havering Council said the state-of-the-art facility will include classrooms, outdoor play areas, a sports hall, a stage and a therapy pool.
The school forms part of Havering’s wider plan to increase specialist educational provision locally and help more children and young people with special educational needs and disabilities access suitable support within their own communities.
How is the school being funded?
Havering Council said the project is being financed through a £38 million grant from the Department for Education. The council has presented the development as a major investment in local specialist education provision.
Councillor Kevin Gill said the progress was significant for a much-anticipated school and said its facilities would improve access for local pupils. He also said the school could reduce the need for children to travel outside the borough to attend provision that meets their needs.
What is the background to the development?
The Balgores Special Free School is being developed to support Havering’s wider SEND strategy. The council’s stated objective is to increase specialist places within the borough and provide support closer to pupils’ communities. The planned intake covers children and young people from four to 19 years old. The £38 million Department for Education grant is funding the construction, while Galliford Try is carrying out the development work.
How could the project affect local families and pupils?
For families of children with special educational needs and disabilities in Havering, the school could provide a larger local option with specialist classrooms, therapy facilities and dedicated spaces for sport and outdoor activity. The council says increased local provision may reduce journeys outside the borough for pupils seeking suitable education. The effect on individual families will depend on admissions arrangements, the school’s opening timetable and whether the available places match local needs. Current construction progress indicates that the planned facilities are moving towards completion, but no confirmed opening date was provided in the council update.